Offshore Wind: EU Approves Up to EUR 9.5 Billion in State Aid for 2 GW in the Netherlands
Münster – The European Commission has approved state aid of up to EUR 9.5 billion for two new offshore wind farms in the Netherlands. The IJmuiden Ver Gamma-A and Gamma-B wind farms, with a combined capacity of 2 GW, are expected to generate up to 7.44 TWh of electricity annually from 2032.
EU Approves EUR 9.5 Billion – Tenders Start at End of November
The European Commission approved the Dutch transitional model TOWOZ (Tijdelijk Ondersteuningsmechanisme Windenergie Op Zee) on November 17, 2026. For the two offshore sites, each with a capacity of around 1 GW, a maximum of EUR 4.758 billion is available for Gamma-A and EUR 4.698 billion for Gamma-B. The total of EUR 9.456 billion represents the maximum state aid framework, not the investment costs of the wind farms. The government has reserved budgetary funds of around EUR 6.2 billion for this purpose; actual payments depend on the bids and on electricity prices.
The award procedure combines two auction models running in parallel. Project developers can bid without state support and offer a concession payment. These bids will be given priority. Bids with state backing will only come into play if no such offers are submitted.
For the state-supported procedure, bid caps of EUR 117/MWh apply for Gamma-A and EUR 116/MWh for Gamma-B. The variable market premium is intended to compensate for the difference between the agreed remuneration value and the relevant electricity market revenues. Repayment rules in case of higher market prices are intended to prevent overcompensation. Support can be granted for 15 years from commissioning.
The Dutch funding agency RVO will accept applications from November 26 to December 10, 2026. Decisions are expected in the first quarter of 2027. In addition to economic requirements, requirements on supply chain diversification, cybersecurity and circular economy apply.
The Netherlands Responds to Failed Offshore Tender
The government had already initiated the return to state-backed offshore tenders in 2025 and specified the model in the first half of 2026. In June, the tender conditions for Gamma-A and Gamma-B were finalised and the financial ceilings were raised. IWR has already reported on this realignment.
A warning sign was the tender for the 1 GW Nederwiek I-A offshore wind farm, for which no bid was received in October 2025. Previously, the government had postponed the tenders for Gamma-A and Gamma-B. Higher project costs, slower-than-expected electrification of industry and uncertainty over long-term electricity marketing are considered burdens.
Additional risks arise from possible grid feed-in charges for power producers. The Dutch regulator ACM is working on corresponding rules. To account for these potential additional costs, the government raised the support framework from EUR 7.896 billion to EUR 9.456 billion in June 2026.
The Gamma-A and Gamma-B offshore wind farms are part of the IJmuiden Ver wind energy zone in the North Sea, with a total planned capacity of around 6 GW. Sites Alpha and Beta were already awarded in 2024; Gamma-A and Gamma-B form the next expansion stage.
Offshore Wind in Europe: Further Billion-Euro Aid Approved for New Projects
The economic difficulties also affect other European countries. At the end of 2024, a 3 GW offshore tender in Denmark received no bids. In August 2025, a German offshore tender for 2.5 GW also received no bids. The German tenders for 2026 were postponed to 2027. In March 2026, the European Commission approved a support model worth around EUR 5 billion for new Danish offshore projects, and on November 10 another state aid scheme worth around EUR 2 billion for the Belgian project Princess Elisabeth Zone Lot 1.
Several European countries are increasingly relying on state revenue support. The UK has used Contracts for Difference (CfD) for years. The Netherlands is also preparing a long-term CfD system. A draft law has been before parliament since June 2026, with entry into force planned for July 2027. In addition, a guarantee fund for long-term power supply contracts is planned.
At the end of 2025, around 4.7 GW of offshore wind capacity was installed in the Netherlands. Around 21 GW is to be reached by 2032; the current roadmap comprises a total of around 23 GW. The difficulties in awarding projects have already led to delays. The expansion target for 2040 was reduced from the original 50 GW to 30 to 40 GW.
With the EU approval, the state aid prerequisite for state support in the upcoming tenders for Gamma-A and Gamma-B has been met.
Source: IWR Online, Nov 11 2026